ENMRWS
15.553
Provide potable surface water to communities in Eastern New Mexico.
This chart shows obligations for the program by fiscal year. All data for this chart was provided by the
administering agency and sourced from SAM.gov, USASpending.gov, and Treasury.gov.
For more information on each of these data sources, please see the
About the data page.
Information not available. The intake structure at Ute Reservoir is constructed. The Phase 1 initial project reached substantial completion in December 2014. At the end of FY15, Reclamation had reimbursed the Authority a total of $7.3 million. FY15 funding of $750,000 (originally for the Elida Pump Station and works) was combined with FY16 appropriations in an agreement modification to initiate the reprioritized Phase 2 of the project, construction of Finished Water (FW) 2B and Cannon Lateral. In FY17, the Authority submitted for USBR review a construction Bid Package 1 memo for Phase II components in the current agreement.
The intake structure at Ute Reservoir is constructed. Phase 1 of the initial project reached substantial completion in December 2014. At the end of FY15, Reclamation had reimbursed the Authority a total of $7.3 million. FY15 funding of $750,000 (originally for the Elida Pump Station and works) was combined with FY16 appropriations in an agreement modification to initiate the re-prioritized Phase 2 of the project, construction of Finished Water (FW) and Cannon Lateral. In FY18, the Authority submitted for USBR review a construction bid package and began construction in the first quarter of FY19. Construction is scheduled to complete in the second quarter of FY20.
In FY 2015, the intake structure at Ute Reservoir is constructed. This initial project reached substantial completion in December 2014.
FY 2015-2020: At the end of FY15, created a Financial Agreement for the construction of Finished Water 2 (FW2) pipeline consisting of approximately 9.25 miles to align the southern end of FW1 pipeline to the city of Clovis finished water tanks; and the Cannon Lateral towards the Cannon Air Force Base finished water tanks. Construction begun in the first quarter of FY19 and finalized in the fourth quarter of FY20.
FY 2020- 2021: During the fourth quarter of FY20, a Financial Agreement for Finished Water 3 (FW3) was created for the construction of approximately 16.8 miles of finished water pipeline, to align the FW2 pipeline in Clovis with the finished water tanks in the city of Portales. Construction of FW3 is scheduled to begin in the fourth quarter of FY21.
During the fourth quarter of FY20, a Financial Agreement for Finished Water 3 (FW3) was created for the construction of approximately 16.8 miles of finished water pipeline, to align the FW2 pipeline in Clovis with the finished water tanks in the city of Portales. Construction of FW3 is scheduled to begin in the fourth quarter of FY21.
In November 2021, Finished Water 3 (FW3) construction begun, it is currently at approximately 50% completion. In September 2021 a new agreement for the construction of FW3 was created. This segment of pipeline is currently starting the bidding process for a construction contract.
Finished Water 3 (FW3) will continue construction. Finished Water 1 (FW1) will begin construction in summer 2023.
Finished Water 3 (FW3) will continue construction. Finished Water 1 (FW1) will begin construction in summer 2023. Design and easement acquisition for all other components in the project.
Finished Water 3 (FW3) will complete construction. Finished Water 1 (FW1) will complete construction. Design and easement acquisition for all other components in the project.
Single Audit Applies (2 CFR Part 200 Subpart F):
For additional information on single audit requirements for this program, review the current Compliance Supplement.
OMB is working with the U.S. Government Accountability Office (GAO) and agency offices of inspectors general to include links to relevant oversight reports. This section will be updated once this information is made available.